Check Completion
Function
This Step is used to check whether all the Basic Move Steps with index (Move by Grid, Move by List, etc) are executed in a single cycle to avoid loops.
Usage Scenario
This Step is usually used together with the Move by Grid and Move by List Steps.
If the Basic Move Steps with index are executed in a single cycle, the Finished exit port will be taken, or else the Unfinished port will be taken.
Parameter Description
General Parameters of Non-Move Steps
Skip Execution
None |
Default setting. Do not skip the current Step. |
Simulation only |
Skip the current Step during simulation. The exit port is specified by Out Port When Skip. |
Always |
Skip the current Step when the project is simulating or running. The exit port is specified by Out Port When Skip. |
Instruction |
When Simulation only or Always is selected, the current Step will be skipped and the subsequent Step will be executed when running the project. If this parameter is set to None in “Check DI” Step in the project, and there is no external input signal during simulation, the project will be stopped when executing to this Step. In this case, setting the parameter to Simulation only or Always enables the simulation to continue. |