This guide shows you how to set up Master-Control communication with a Hyundai robot.

Check Controller and Software Version

  • Robot controller version: Hi5a-S (Hi5a-T10 is not supported).

  • Mech-Mind Software Suite: 1.6.0 or above.

Set up the Network Connection

Connect the Hardware

Plug the Ethernet cable of the IPC into the CNETN3 port inside the controller or the Ethernet port on the outside, as shown below.

hardware connection
There are three port inside the controller, namely CNETN1, CNETN2, and CNETN3, which correspond to the EN0 address, TP address and EN2 User Ethernet address on the teach pendant respectively. Therefore, the Ethernet cable should be connected to the CNETN3 port.

Set the IP Address

  1. On the teach pendant, go to System  Control parameter  Network  Environment setting.

    system
    control parameter
    network
    environment setting
  2. Select EN2(Public), and set the right IP Address. Please also make sure that the Sebnet Mask is set to 255.255.255.0.

    set ip
    • The robot IP should be in the same subnet as the IPC.

    • The subnet mask of the IPC is the same as that of the robot, which is 255.255.255.0.

    • Restart the robot after modifying the IP address.

Load the Program Files to the Robot

  1. Connect the USB flash drive to the teach pendant.

    To control a HYUNDAI robot, our master-control program 0101.JOB and* 0102.JOB* need to be initialized by changing the Program File Format Version information on the first line.

    If you already have other available program on the robot, please directly copy and paste the program into the flash drive and skip to step 5.
  2. Select Command input.

    load file 1
  3. Choose either of the command to input, as shown below.

    load file 2
  4. Now you can see the robot version information on the top. Then save the program.

    load file 3
  5. Select the newly created program file (or a previous program file), and select Copy. Then switch to the USB folder and select Paste.

  6. Connect the flash drive to the IPC. Open the program, and then copy the first line.

  7. Open the two master-control program files 0101.JOB and 0102.JOB(The files are stored in xxx{company} Software Suite-x.x.x`Mech-Center\Robot_Server\Robot_FullControl\hyundai\Hi5a-S`.) and paste the copied code to replace the first line in the program, and then save the changes.

    change file
  8. Copy and paste the master-control program files 0101.JOB and 0102.JOB into the flash drive. Connect the flash drive to the teach pendant. Go to System  File manager  USB, select 0101.JOB and 0102.JOB, and then select Copy. Then switch to T/P, select Paste to load the files to the robot.

    change file 1

Further Configuration

  1. Change the IP address of the IPC to 192.168.0.150.

    • This IP address is a default one which is specified in 0101.JOB and 0102.JOB. If you need to change the IP address, please modify the IP address in the program accordingly.

    • The new IP address should be in the same subnet as that of the robot controller.

  2. Set the management IP address of the router to 192.168.0.1.

  3. Go to System  User Environment.

    system
    user environment
  4. Select User key, and enter 314 to request permission.

    user key
  5. Change the P Coordinate* to Axis.

    • Select Axis on the screen directly.

    • Press SHIFT on the teach pendant and simultaneously press the left or right arrow keys to move left or right.

      keyboard
      If the joint information has not been modified, the following error message will appear in the background.
    error information

Test Robot Connection

Check Mech-Center Settings

  1. Open Mech-Center and click *Deployment Settings *icon setting.

  2. Go to Robot Server, check if the robot model displayed after Robot type in the project matches the one in use.

  3. Set the robot IP address to the IP address of the IPC and select Save.

test robot connection

Connect to the Robot

  1. Click Master-control Robot icon 1 in the Mech-Center toolbar.

  2. Switch the robot into AUTO mode.

  3. Reset the program steps of the robot to 0 for both program 101 and program 102. Select Program  Step/Function, and enter 0 in the pop-up Step selection window.

    reset step 0
    Execute the program 0101.JOB.
  4. If the robot is successfully connected, a robot icon with the robot model will be displayed in the Mech-Center Service Status bar, and the corresponding message is printed in the Log panel.

Reconnect the Robot

  1. Under teach mode, press R.. [NO], enter 314 and then press ENTER [YES] to request permission.

    get permission
  2. Each time when reconnect the robot, the background tasks should be stopped and the step in the foreground program should be reset to 0. Select Service‣ Monitoring ‣ Multi-tasking_state ‣ ENTER [YES] to enter the multi-tasking interface.

    service
    monitoring
    multi tasking state
  3. Select Program (Suntask) and then select Selection. Enter 3 in the Program selection window and then press ENTER [YES] to complete configuration.

    reset pointer 0

We Value Your Privacy

We use cookies to provide you with the best possible experience on our website. By continuing to use the site, you acknowledge that you agree to the use of cookies. If you decline, a single cookie will be used to ensure you're not tracked or remembered when you visit this website.