The Execution Flags in the Step Parameters panel include many Step common parameters that can be adjusted. The adjustment of the parameters will affect the execution results of the Steps, and then change the result of the whole project.

This chapter will introduce the common parameters of the Steps.

Visualize Outputs

The Visualize Outputs parameter is used to select whether to view the visualized output of the Step.

Select Debug Output on the right side of the project toolbar, and then select Visualize Outputs. After doing so, you can view the visualized output of the Step in the upper-right Debug Output panel when running the Step, which is shown in the following figure. Then, you can judge the execution status according to the result, and adjust the Step parameters to achieve a desirable result.

show output

The Visualize Outputs parameter works the same as open eye icon in the Step interface does.

The Visualize Outputs parameter can be interconnected with the eye icon open eye icon. Selecting this parameter corresponds to an opened eye icon open eye icon, and unselecting this parameter corresponds to a closed eye icon close eye icon.

Show Outputs as Text

The Show Outputs as Text parameter is used to select whether to display text message when the Step execution ends.

After selecting this parameter, you can view the relevant text message when the Step execution ends, which is shown in the following figure. Then, you can judge the execution status according to the text message, and adjust the Step parameters to achieve a desirable result.

show text

Reuse Input

The Reuse Input parameter is used to select whether to align the number of list items of the two input ports.

This parameter is usually applied in the Steps under the group of Pose2. For example, when there is only one pose in the first input port of the Step, while there are three poses in the second input port, the existed pose in the first input port will be duplicated twice after the Reuse Input parameter is selected, and so the number of poses in the two input ports remains the same.

Continue Given No Output

When there is no output from one Step in the project, the Continue Given No Output parameter is used to select whether to continue to run the project.

After selecting this parameter, the project will continue to run even if there is no output from one Step.

Reload File

The Reload File parameter is used to select whether to reload the relevant files each time the project is run.

  • If the parameter is unselected, after the loaded file in the Step is updated with the same file name, the updated contents cannot be used when the Step is executed again.

  • If the parameter is selected, after the loaded file in the Step is updated with the same file name, the updated contents can be used when the Step is executed again.

    For example, in the Calc Results by Python Step, if the script file is updated and Reload File is selected, the updated script file will be loaded after rerunning this Step.

  • If you change the path of the loaded file, you will be informed a file path error when you run the project.

  • For the “Capture Images from Camera” Step, the camera calibration parameters will not be reloaded when Reload File is selected.

  • Selecting Reload File triggers additional file I/O operations during project running, which may increase the overall runtime of the project.

Trigger Control Flow Given No Output

When the current Step does not generate output data, the "Trigger Control Flow Given No Output" parameter can be used to control whether to trigger the control flow output of this Step. This parameter is suitable for scenarios where subsequent logic still needs to be triggered or a fallback flow needs to be executed when a Step has no output.

After this parameter is enabled, if a Step has no output data after running, the control flow is triggered so that the project continues to run downward. If it is not enabled and the Step has no output data, the control flow is not triggered, and subsequent Steps that depend on this control flow do not run.

trigger control flow

Trigger Control Flow Given Output

When there is an output from the current Step, the Trigger Control Flow Given Output parameter is used to select whether to trigger the control flow.

Notify Procedure Finished When No Output

When there is no output from one Step in the project, the Notify Procedure Finished When No Output parameter is used to select whether to notify people of the empty project output and then end the running project.

The figure 1 below is the Step operation log when this parameter is unselected, while the figure 2 below is the Step operation log when this parameter is selected.

show project status

Is this page helpful?

You can give a feedback in any of the following ways:

We Value Your Privacy

We use cookies to provide you with the best possible experience on our website. By continuing to use the site, you acknowledge that you agree to the use of cookies. If you decline, a single cookie will be used to ensure you're not tracked or remembered when you visit this website.