Adjust Project ID¶
When “Autoload Solution” is selected, the projects belonging to the solution will be autoloaded as well. Each project will be assigned a project ID, as shown below.
![../../../../_images/adjust_project_number_1.png](../../../../_images/adjust_project_number_1.png)
To adjust the display order of the project in the project list, select and drag the project. The result before and after adjusting is shown below.
![../../../../_images/adjust_project_number_2.png](../../../../_images/adjust_project_number_2.png)
To reset the project ID, right-click the solution or one of the projects, and select Reset Project IDs. The disordered project IDs will be re-sorted in descending order, and the project corresponding to each ID will be changed.
![../../../../_images/adjust_project_number_3.png](../../../../_images/adjust_project_number_3.png)
The result before and after resetting the project IDs is shown below.
![../../../../_images/adjust_project_number_4.png](../../../../_images/adjust_project_number_4.png)